Millstream Road Bridges

Project Description

The replacement of the bridges over the Kishwaukee River and South Branch Kishwaukee River.

Click here for Transportation Programs

Project Location Map 

Millstream

Project Status

Phase I preliminary engineering is completed
Phase II design engineering is completed
Phase III construction is underway and is anticipated to completed in 2025. 

Public Involvement Opportunities 

Click here to leave feedback on this project

Available Documents

Project Development Report
Record Structural Plans (056-3022)
Record Structural Plans (056-3023)
Structure Geotechnical Report (056-3022)
Structure Geotechnical Report (056-3023)
Structure Geotechnical Report (Retaining Walls) 
Roadway Geotechnical Report
Location Drainage Study
Location Drainage Study (ComEd Easement)
Hydraulic Report
Existing Agricultural Drain Tile Investigation
Special Waste Assessment
Environmental Report for LPC 663

Contact Information

Scott Czaplicki, P.E.
MCDOT Project Manager
sdczaplicki@transystems.com

 

Scope of Work Municipality County Board District
Bridge Replacement Unincorporated  Seneca Township District 8
Category Lead Agency Total Cost
Preservation McHenry County DOT

$9,617,881
(Construction Cost)