The replacement of the bridges over the Kishwaukee River and South Branch Kishwaukee River.
Click here for Transportation Programs
Project Location Map
Project Status
Phase I preliminary engineering is completed
Phase II design engineering is completed
Phase III construction is underway and is anticipated to completed in 2025.
Public Involvement Opportunities
Click here to leave feedback on this projectAvailable Documents
Project Development Report
Record Structural Plans (056-3022)
Record Structural Plans (056-3023)
Structure Geotechnical Report (056-3022)
Structure Geotechnical Report (056-3023)
Structure Geotechnical Report (Retaining Walls)
Roadway Geotechnical Report
Location Drainage Study
Location Drainage Study (ComEd Easement)
Hydraulic Report
Existing Agricultural Drain Tile Investigation
Special Waste Assessment
Environmental Report for LPC 663
Contact Information
Scott Czaplicki, P.E.
MCDOT Project Manager
sdczaplicki@transystems.com
| Scope of Work | Municipality | County Board District | ||
| Bridge Replacement | Unincorporated Seneca Township | District 8 | ||
| Category | Lead Agency | Total Cost | ||
| Preservation | McHenry County DOT |
$9,617,881 |