McHenry County, IL
Home MenuHunter Road Bridge
Project Description
The replacement of an existing bridge over the Little Beaver Creek.
Click here for Transportation Programs
Project Location Map
Project Status
Phase I preliminary engineering is completed.
Phase II design engineering is underway.
Construction is anticipated to start in 2025
Public Involvement Opportunities
Click here to leave feedback on this project
Available Documents
Hunter Road Bridge Detour
Bridge Inspection Report 2024
Existing Agricultural Drain Tile Investigation
Existing Bridge Plans
Hydraulic Report
Location Drainage Study
LPC 663
Preliminary Environmental Site Assessment
Preliminary Site Investigation
Special Waste Assessment
Structural Geotechnical Report
Contact Information
Scott Czaplicki, P.E.
MCDOT Project Manager
sdczaplicki@transystems.com
| Scope of Work | Municipality | County Board District | ||
| Bridge Replacement | Unincorporated Chemung Township | District 8 | ||
| Category | Lead Agency | Total Cost | ||
| Preservation | McHenry County DOT | $2,650,000 |